Timeline
BMRCL Proposed The Lines
2013
RITES Awarded To Prepare Feasibility Study
2014
Phase 2A (ORR Metro) DPR Prepared & Submitted To State Govt
2016
State Govt Approved Phase 2A DPR
March 2017
MoHUA Floats New Metro Rail Policy
August 2017
Revised Phase 2A (ORR Metro) & Phase 2B (Airport Metro) DPR Prepared As Per New Metro Rail Policy & Submitted to GoI
2019
Detailed Design Consultancy For ORR & Airport Metro Tender Awarded In 2 Packages To SMEC & AECOM
February 2020
GoI Approved Phase 2A & 2B DPR
April 2021
ORR Metro Civil Tender Awarded In 2 Packages To Afcons & SNC
May 2021
Detailed Design Consultancy Tender For Baiyappanahalli Depot and Doddajala Depot Awarded To Padeco Co. LTD
September 2021
ORR Metro Civil Work Begins
September 2021
Airport Metro Civil Tender Awarded In 3 Packages To NCC
November 2021
Airport Metro Civil Work Begins
February 2022
Baiyappanahalli & Doddajala Depot Civil Tenders Awarded To J Kumar-AICPL JV
March 2023
Doddajala Depot Civil Work Begins
June 2023
Tender For Track Works In ORR & Airport Metro Awarded To L&T
June 2023
Rolling Stock Tender For ORR & Airport Metro Awarded To BEML
August 2023
Baiyappanahalli Depot Civil Work Begins
September 2023
Signaling, Telecommunication & PSD Tender For ORR & Airport Metro Awarded To Alstom
January 2024
1st Completed Stretch In ORR Handed Over By SNC For Track Work
April 2024
Third Rail Tender Awarded To Siemens-RVNL JV
June 2024
Track Work Begins Between Saraswathinagara To Doddanekundi
July 2024
Track Work Begins Between At Jakkur In Airport Line Package 2
August 2024
Manufacturing Of Prototype Train Begins
August 2024
Track Work Begins Near Airport Terminal In Airport Line Package 3
September 2024
1st Completed Stretch Handed Over By Afcons For Track Work
November 2024
Track Work Begins Between Ibbaluru To Kadubeesanahalli
November 2024
Architectural Finishing Of ORR Metro PKG 1 Stations Awarded To MR Constructions
November 2024
Architectural Finishing Of ORR Metro PKG 2 Stations Awarded To Godrej & Boyce Mfg. Co. Ltd
December 2024
Veerannapalya Station Balance Civil Works Awarded To URC Construction Pvt Ltd
February 2025
E&M Tender For Phase 2A & 2B Awarded To Jakson Ltd
February 2025
Escalators & Travelators Tender Awarded To Johnson Lifts Pvt Ltd
February 2025
1st Station Roof Work Beings At Saraswathinagara Station
February 2025
Architectural Finishing Works Commences At ORR Metro Stations
March 2025