Cumulative Progress
Piers
96% +0%
Caps + Beams + Tiebeams
84% +2%
Girders
75% +1%
Breakup
STANDALONE PIERS
95%
PIER CAPS
84%
PORTAL PIERS
100%
PORTAL BEAMS
84%
U GIRDER SPANS
80%
I GIRDER SPANS
13%
STEEL GIRDER SPANS
20%
HIGHLIGHTS:

  • 300th Pier cap launched.
  • Construction of a new bridge at Doddajala service road is ongoing to extend the bridge & divert traffic to take up pier work.

FEBRUARY

2025

ISSUES:

  • Pending construction of a new bridge to divert traffic on service road has held up works of 4 piers at Doddajala. This is delaying the continuity of the viaduct.

Progress In The Month
U Girders Progress In Last 6 Months
STATIONS PROGRESS
Select Station:
DESCRIPTIONTOTALCOMPLETEDCOMPLETION
Piers GL To CL
1616
CCL Beams
88
Pier CL To TL
1616
PFL Beams
88
CCL RCC/I-Girders
6555
PFL RCC/I-Girders
3731
U Girders
1411
Doddajala Station's Progress In 3D

USE MOUSE TO ZOOM, PAN, AND ROTATE THE MODEL. SCROLL TO ZOOM IN AND OUT. DRAG TO ROTATE. SHIFT+DRAG TO PAN. PINCH ZOOM ON MOBILE

NOTE ON STATION'S PROGRESS TABLE:
    • STATION'S PROGRESS BEING REPORTED CONSISTS ONLY OF MAIN GRID IN MEDIAN. OTHER THAN THIS, SECONDARY WING PIERS ON SERVICE ROAD MEDIAN, SECONDARY WING CAPS, GIRDERS, CONCOURSE SLAB, PLATFORM SLAB, SECONDARY WING SLAB, ENTRY/EXIT STRUCTURE COLUMNS, STAIRCASES, ROOMS, ROOF ETC WORKS ARE NOT BEING TRACKED AS THE SCOPE DATA IS NOT AVAILABLE AND ALSO DIFFICULT TO TRACK BY PUBLIC DUE TO VISIBILITY ISSUES.
  • Girders Progress
    Girders Progress
    Gallery Image 1

    Ongoing Bridge Expansion Works At Doddajala

    © Photo Copyright: Sunil
    Gallery Image 2

    Underground Portion Works Near IAF

    © Photo Copyright: Sunil
    Gallery Image 3

    Stepped Portion Casting On AP790 Pier Cap

    © Photo Copyright: Sunil
    Video Of Progress As Of March 7th 2025: By Sunil