Construction of a new bridge at Doddajala service road is ongoing to extend the bridge & divert traffic to take up pier work.
FEBRUARY
2025
ISSUES:
Pending construction of a new bridge to divert traffic on service road has held up works of 4 piers at Doddajala. This is delaying the continuity of the viaduct.
Progress In The Month
U Girders Progress In Last 6 Months
STATIONS PROGRESS
Select Station:
DESCRIPTION
TOTAL
COMPLETED
COMPLETION
Piers GL To CL
16
16
CCL Beams
8
8
Pier CL To TL
16
16
PFL Beams
8
8
CCL RCC/I-Girders
65
55
PFL RCC/I-Girders
37
31
U Girders
14
11
Doddajala Station's Progress In 3D
USE MOUSE TO ZOOM, PAN, AND ROTATE THE MODEL. SCROLL TO ZOOM IN AND OUT. DRAG TO ROTATE. SHIFT+DRAG TO PAN. PINCH ZOOM ON MOBILE
NOTE ON STATION'S PROGRESS TABLE:
STATION'S PROGRESS BEING REPORTED CONSISTS ONLY OF MAIN GRID IN MEDIAN. OTHER THAN THIS, SECONDARY WING PIERS ON SERVICE ROAD MEDIAN, SECONDARY WING CAPS, GIRDERS, CONCOURSE SLAB, PLATFORM SLAB, SECONDARY WING SLAB, ENTRY/EXIT STRUCTURE COLUMNS, STAIRCASES, ROOMS, ROOF ETC WORKS ARE NOT BEING TRACKED AS THE SCOPE DATA IS NOT AVAILABLE AND ALSO DIFFICULT TO TRACK BY PUBLIC DUE TO VISIBILITY ISSUES.