Milestone Achieved: 100% Piling completed in the scope.
Launching of all station arms completed at Doddanekundi Station. With this, all precast station arms completed in the scope.
Launching of all U Girders completed at KR Pura Station.
1st I-Girder of Marathahalli Station launched.
DECEMBER
2024
Progress In The Month
U Girders Progress In Last 6 Months
STATIONS PROGRESS
Select Station:
DESCRIPTION
TOTAL
COMPLETED
COMPLETION
Piers GL To CL
8
8
CCL Pier Cap
8
8
Pier CL To TL
9
8
PFL Pier Cap
9
8
PFL Arms
16
16
CCL Arms
16
16
CCL RCC/I-Girders
42
36
PFL RCC/I-Girders
28
24
U Girders
14
12
Kodibeesanahalli Station's Progress In 3D
Coming
Later
NOTE ON STATION'S PROGRESS TABLE:
STATION'S PROGRESS BEING REPORTED CONSISTS ONLY OF MAIN GRID IN MEDIAN. OTHER THAN THIS, SECONDARY WING PIERS ON SERVICE ROAD MEDIAN, SECONDARY WING CAPS, GIRDERS, CONCOURSE SLAB, PLATFORM SLAB, SECONDARY WING SLAB, ENTRY/EXIT STRUCTURE COLUMNS, STAIRCASES, ROOMS, ROOF ETC WORKS ARE NOT BEING TRACKED AS THE SCOPE DATA IS NOT AVAILABLE AND ALSO DIFFICULT TO TRACK BY PUBLIC DUE TO VISIBILITY ISSUES.