Cumulative Progress
Piers
100%
Caps + Beams + Tiebeams
98% +0%
Girders
94% +2%
Breakup
STANDALONE PIERS
100%
PIER CAPS
99%
PORTAL PIERS
100%
PORTAL BEAMS
88%
SPLIT PORTAL PIERS
100%
SPLIT PORTAL TIEBEAMS
100%
U GIRDER SPANS
99%
I GIRDER SPANS
72%
STEEL GIRDER SPANS
55%
HIGHLIGHTS:

  • Launching all precast girders of Marathahalli Station completed.
  • Assembling of parts of Steel Composite Girder over railway track near Benniganahalli has commenced.

JULY

2025

Progress In The Month
U Girders & I Girders Progress In Last 6 Months
NOTE ON STATION'S PROGRESS:
    • ALL PUBLICLY TRACKABLE STATION'S PROGRESS ARE COMPLETED. REMAINING STATION WORK LIKE SECONDARY WING PIERS ON SERVICE ROAD MEDIAN, SECONDARY WING CAPS, CONCOURSE SLAB, PLATFORM SLAB, SECONDARY WING SLAB, ENTRY/EXIT STRUCTURE COLUMNS, STAIRCASES, ROOMS, ROOF ETC CONTINUES. THESE WORKS ARE NOT BEING TRACKED AS THE SCOPE DATA IS NOT AVAILABLE AND ALSO DIFFICULT TO TRACK BY PUBLIC DUE TO VISIBILITY ISSUES.
  • Girders Progress
    Girders Progress
    Gallery Image 1

    ORDP13 Portal Beam Tied At BYP Depot Link Line

    © Photo Copyright: Aditya
    Gallery Image 2

    Composite Girder Assembly Begins Over Benniganahalli Railway Track

    © Photo Copyright: Aditya
    Gallery Image 3

    Upper Line & Lower Line Towards BYP Depot

    © Photo Copyright: Aditya
    Video Of Progress As Of July 13th 2025: By Sunil