Launching all precast girders of Marathahalli Station completed.
Assembling of parts of Steel Composite Girder over railway track near Benniganahalli has commenced.
JULY
2025
Progress In The Month
U Girders & I Girders Progress In Last 6 Months
NOTE ON STATION'S PROGRESS:
ALL PUBLICLY TRACKABLE STATION'S PROGRESS ARE COMPLETED. REMAINING STATION WORK LIKE SECONDARY WING PIERS ON SERVICE ROAD MEDIAN, SECONDARY WING CAPS, CONCOURSE SLAB, PLATFORM SLAB, SECONDARY WING SLAB, ENTRY/EXIT STRUCTURE COLUMNS, STAIRCASES, ROOMS, ROOF ETC CONTINUES. THESE WORKS ARE NOT BEING TRACKED AS THE SCOPE DATA IS NOT AVAILABLE AND ALSO DIFFICULT TO TRACK BY PUBLIC DUE TO VISIBILITY ISSUES.