Cumulative Progress
Piers
66% +1%
Caps + Beams + Tiebeams
50% +0%
Girders
44% +1%
Breakup
STANDALONE PIERS
71%
PIER CAPS
54%
PORTAL PIERS
48%
PORTAL BEAMS
16%
U GIRDER SPANS
52%
I GIRDER SPANS
0%
STEEL GIRDER SPANS
7%
OWG
0%
HIGHLIGHTS:

  • Casting of all platform portal beams completed at Yelahanka Station.

DECEMBER

2024

ISSUES:

  • A large section between Kempapura to Hebbal is yet to be permitted to take up works. Approval is being given section by section to not affect traffic flow.
  • Tree clearance permission pending for few piers near Kempapura, Embassy Lake Terraces, Godrej Platinum

Progress In The Month
U Girders Progress In Last 6 Months
STATIONS PROGRESS
Select Station:
DESCRIPTIONTOTALCOMPLETEDCOMPLETION
Piers GL To CL
163
CCL Beams
80
Pier CL To DL
160
DFL Beams
80
Pier DL To TL
160
PFL Beams
80
CCL RCC/I-Girder Spans
70
DFL RCC/I-Girder Spans
70
PFL RCC/I-Girder Spans
70
U Girders
140
Hebbal Station's Progress In 3D

USE MOUSE TO ZOOM, PAN, AND ROTATE THE MODEL. SCROLL TO ZOOM IN AND OUT. DRAG TO ROTATE. SHIFT+DRAG TO PAN. PINCH ZOOM ON MOBILE

NOTE ON STATION'S PROGRESS TABLE:
    • STATION'S PROGRESS BEING REPORTED CONSISTS ONLY OF MAIN GRID IN MEDIAN. OTHER THAN THIS, SECONDARY WING PIERS ON SERVICE ROAD MEDIAN, SECONDARY WING CAPS, GIRDERS, CONCOURSE SLAB, PLATFORM SLAB, SECONDARY WING SLAB, ENTRY/EXIT STRUCTURE COLUMNS, STAIRCASES, ROOMS, ROOF ETC WORKS ARE NOT BEING TRACKED AS THE SCOPE DATA IS NOT AVAILABLE AND ALSO DIFFICULT TO TRACK BY PUBLIC DUE TO VISIBILITY ISSUES.
  • Girders Progress
    Girders Progress
    Gallery Image 1

    Concourse Deck Slab Cast At Bagalur Cross Station

    © Photo Copyright: K Vinay Kumar
    Gallery Image 2

    Piers Getting Ready Near Esteem Mall

    © Photo Copyright: Sunil
    Gallery Image 3

    Shuttering For Portal Beam AP481

    © Photo Copyright: Sunil
    Video Of Progress As Of Dec 7th 2024: By Sunil