Cumulative Progress
Piers
74% +3%
Caps + Beams + Tiebeams
56% +2%
Girders
49% +2%
Breakup
STANDALONE PIERS
77%
PIER CAPS
59%
PORTAL PIERS
60%
PORTAL BEAMS
28%
U GIRDER SPANS
57%
I GIRDER SPANS
7%
STEEL GIRDER SPANS
15%
OWG
0%
HIGHLIGHTS:

  • 1st I-Girder of viaduct scope launched.
  • Launching of all RCC & I-Girders of Yelahanka Station completed.
  • 1st Concourse Beam of Kodigehalli Station cast.
  • 400th U Girder launched.
  • High Court finally permitted to cut trees at Kempapura & near Esteem mall.

MARCH

2025

ISSUES:

  • Shifting of FOB pending near Bagalur Cross Station

Progress In The Month
U Girders Progress In Last 6 Months
STATIONS PROGRESS
Select Station:
DESCRIPTIONTOTALCOMPLETEDCOMPLETION
Piers GL To CL
168
CCL Beams
80
Pier CL To PD
160
PDL Beams
80
Pier PD To TL
160
PFL Beams
80
CCL RCC/I-Girders
710
DFL RCC/I-Girders
700
PFL RCC/I-Girders
500
U Girders
140
Hebbal Station's Progress In 3D

USE MOUSE TO ZOOM, PAN, AND ROTATE THE MODEL. SCROLL TO ZOOM IN AND OUT. DRAG TO ROTATE. SHIFT+DRAG TO PAN. PINCH ZOOM ON MOBILE

NOTE ON STATION'S PROGRESS TABLE:
    • STATION'S PROGRESS BEING REPORTED CONSISTS ONLY OF MAIN GRID IN MEDIAN. OTHER THAN THIS, SECONDARY WING PIERS ON SERVICE ROAD MEDIAN, SECONDARY WING CAPS, GIRDERS, CONCOURSE SLAB, PLATFORM SLAB, SECONDARY WING SLAB, ENTRY/EXIT STRUCTURE COLUMNS, STAIRCASES, ROOMS, ROOF ETC WORKS ARE NOT BEING TRACKED AS THE SCOPE DATA IS NOT AVAILABLE AND ALSO DIFFICULT TO TRACK BY PUBLIC DUE TO VISIBILITY ISSUES.
  • Girders Progress
    Girders Progress
    Gallery Image 1

    Down Line Piers Taking Shape Between Kempapura-Hebbal

    © Photo Copyright: Sunil
    Gallery Image 2

    AP725 Pier Cap Launching Works Near IAF

    © Photo Copyright: Sunil
    Gallery Image 3

    Pier Cap Under Portal Beam Works Ongoing Near Kogilu Cross

    © Photo Copyright: Sunil
    Video Of Progress As Of March 7th 2025: By Sunil