Cumulative Progress
Piers
59% +2%
Caps + Beams + Tiebeams
46% +2%
Girders
23% +2%
Breakup
STANDALONE PIERS
77%
PIER CAPS
63%
PORTAL PIERS
30%
PORTAL BEAMS
0%
SPLIT PORTAL PIERS
58%
SPLIT PORTAL TIEBEAMS
39%
U GIRDER SPANS
28%
I GIRDER SPANS
0%
STEEL GIRDER SPANS
4%
HIGHLIGHTS:

  • 1st full length split flyover pier of Hennur Underpass has been cast.
  • 1st U Girder of Kalyannagara Flyover launched.
  • Launching of all Platform Pier Caps of HRBR Layout Station completed.
  • KPTCL tower at Banaswadi dismantled.

MARCH

2025

ISSUES:

  • Delays in Kasturinagara, Horamavu, HBR Layout station works.
  • Shifting of HT lines pending at multiple locations.

Progress In The Month
U Girders Progress In Last 6 Months
STATIONS PROGRESS
Select Station:
DESCRIPTIONTOTALCOMPLETEDCOMPLETION
Piers GL To CL
87
CCL Pier Cap
80
Pier CL To TL
80
PFL Pier Cap
80
PFL Arms
160
CCL Arms
160
CCL RCC/I-Girder Spans
70
PFL RCC/I-Girder Spans
70
U Girders
140
Kasturinagara Station's Progress In 3D

Coming

Later

NOTE ON STATION'S PROGRESS TABLE:
    • STATION'S PROGRESS BEING REPORTED CONSISTS ONLY OF MAIN GRID IN MEDIAN. OTHER THAN THIS, SECONDARY WING PIERS ON SERVICE ROAD MEDIAN, SECONDARY WING CAPS, GIRDERS, CONCOURSE SLAB, PLATFORM SLAB, SECONDARY WING SLAB, ENTRY/EXIT STRUCTURE COLUMNS, STAIRCASES, ROOMS, ROOF ETC WORKS ARE NOT BEING TRACKED AS THE SCOPE DATA IS NOT AVAILABLE AND ALSO DIFFICULT TO TRACK BY PUBLIC DUE TO VISIBILITY ISSUES.
  • Girders Progress
    Girders Progress
    Gallery Image 1

    HRBR Station

    © Photo Copyright: Sunil
    Gallery Image 2

    Kempapura Station

    © Photo Copyright: Sunil
    Gallery Image 3

    Ongoing Works At Nagawara Flyover

    © Photo Copyright: Sunil
    Video Of Progress As Of March 9th 2025: By Sunil