Cumulative Progress
Piers
62% +1%
Caps + Beams + Tiebeams
52% +4%
Girders
25% +1%
Breakup
STANDALONE PIERS
79%
PIER CAPS
67%
PORTAL PIERS
32%
PORTAL BEAMS
0%
SPLIT PORTAL PIERS
63%
SPLIT PORTAL TIEBEAMS
49%
U GIRDER SPANS
29%
I GIRDER SPANS
0%
STEEL GIRDER SPANS
8%
HIGHLIGHTS:

  • 2nd composite girder of Kalyannagara Flyover launched.

MAY

2025

ISSUES:

  • Delays in Station works.
  • Delays in eccentric pier caps between Veerannapalya to HBR Layout Station.
  • Delays in Pier works between Benniganahalli to Kasturinagara.
  • Scheduling delay in getting the deck slab over composite girder ready before the LG arrived at Kalyannagara Flyover. Due to which, LG is now lying idle.

Progress In The Month
U Girders Progress In Last 6 Months
STATIONS PROGRESS
Select Station:
DESCRIPTIONTOTALCOMPLETEDCOMPLETION
Piers GL To CL
87
CCL Pier Cap
80
Pier CL To TL
80
PFL Pier Cap
80
PFL Arms
160
CCL Arms
160
CCL RCC/I-Girder Spans
70
PFL RCC/I-Girder Spans
70
U Girders
140
Kasturinagara Station's Progress In 3D

Coming

Later

NOTE ON STATION'S PROGRESS TABLE:
    • STATION'S PROGRESS BEING REPORTED CONSISTS ONLY OF MAIN GRID IN MEDIAN. OTHER THAN THIS, SECONDARY WING PIERS ON SERVICE ROAD MEDIAN, SECONDARY WING CAPS, GIRDERS, CONCOURSE SLAB, PLATFORM SLAB, SECONDARY WING SLAB, ENTRY/EXIT STRUCTURE COLUMNS, STAIRCASES, ROOMS, ROOF ETC WORKS ARE NOT BEING TRACKED AS THE SCOPE DATA IS NOT AVAILABLE AND ALSO DIFFICULT TO TRACK BY PUBLIC DUE TO VISIBILITY ISSUES.
  • Girders Progress
    Girders Progress
    Gallery Image 1

    Piling Works At Manyata Tech Park

    © Photo Copyright: Aditya
    Gallery Image 2

    2nd Composite Girder Launched At Kalyanagara Flyover

    © Photo Copyright: Aditya
    Gallery Image 3

    Veerannapalya Flyover

    © Photo Copyright: Aditya
    Video Of Progress As Of May 4th 2025: By Sunil