1st Split Portal Pier of Nagawara Flyover has been cast.
1st Split Portal Pier of Hennur Flyover has been cast.
1st Platform Arm of HRBR Layout Station launched.
BWSSB pipeline shifting works completed at Rammurthynagar Underpass. Piling work commenced.
DECEMBER
2024
ISSUES:
Pending railway permission to take up works at Benniganahalli
Pending KPTCL tower dismantling which is obstructing metro viaduct
Delays in Kasturinagara and Horamavu station works
Shifting of HT lines pending at multiple locations
Pending site access for Up line viaduct piers at Kempapura, including for Kempapura Station
Progress In The Month
U Girders Progress In Last 6 Months
STATIONS PROGRESS
Select Station:
DESCRIPTION
TOTAL
COMPLETED
COMPLETION
Piers GL To CL
8
7
CCL Pier Cap
8
0
Pier CL To TL
8
0
PFL Pier Cap
8
0
PFL Arms
16
0
CCL Arms
16
0
CCL RCC/I-Girders
7
0
PFL RCC/I-Girders
7
0
U Girders
14
0
Kasturinagara Station's Progress In 3D
Coming
Later
NOTE ON STATION'S PROGRESS TABLE:
STATION'S PROGRESS BEING REPORTED CONSISTS ONLY OF MAIN GRID IN MEDIAN. OTHER THAN THIS, SECONDARY WING PIERS ON SERVICE ROAD MEDIAN, SECONDARY WING CAPS, GIRDERS, CONCOURSE SLAB, PLATFORM SLAB, SECONDARY WING SLAB, ENTRY/EXIT STRUCTURE COLUMNS, STAIRCASES, ROOMS, ROOF ETC WORKS ARE NOT BEING TRACKED AS THE SCOPE DATA IS NOT AVAILABLE AND ALSO DIFFICULT TO TRACK BY PUBLIC DUE TO VISIBILITY ISSUES.
Girders Progress
Assembly Of LG In Progress Near Kalyannagara Flyover