1st full length split flyover pier of Hennur Underpass has been cast.
1st U Girder of Kalyannagara Flyover launched.
Launching of all Platform Pier Caps of HRBR Layout Station completed.
KPTCL tower at Banaswadi dismantled.
MARCH
2025
ISSUES:
Delays in Kasturinagara, Horamavu, HBR Layout station works.
Shifting of HT lines pending at multiple locations.
Progress In The Month
U Girders Progress In Last 6 Months
STATIONS PROGRESS
Select Station:
DESCRIPTION
TOTAL
COMPLETED
COMPLETION
Piers GL To CL
8
7
CCL Pier Cap
8
0
Pier CL To TL
8
0
PFL Pier Cap
8
0
PFL Arms
16
0
CCL Arms
16
0
CCL RCC/I-Girder Spans
7
0
PFL RCC/I-Girder Spans
7
0
U Girders
14
0
Kasturinagara Station's Progress In 3D
Coming
Later
NOTE ON STATION'S PROGRESS TABLE:
STATION'S PROGRESS BEING REPORTED CONSISTS ONLY OF MAIN GRID IN MEDIAN. OTHER THAN THIS, SECONDARY WING PIERS ON SERVICE ROAD MEDIAN, SECONDARY WING CAPS, GIRDERS, CONCOURSE SLAB, PLATFORM SLAB, SECONDARY WING SLAB, ENTRY/EXIT STRUCTURE COLUMNS, STAIRCASES, ROOMS, ROOF ETC WORKS ARE NOT BEING TRACKED AS THE SCOPE DATA IS NOT AVAILABLE AND ALSO DIFFICULT TO TRACK BY PUBLIC DUE TO VISIBILITY ISSUES.