Cumulative Progress
Piers
97% +0%
Caps + Beams + Tiebeams
94% +2%
Girders
62% +3%
Breakup
STANDALONE PIERS
99%
PIER CAPS
91%
PORTAL PIERS
0%
PORTAL BEAMS
0%
SPLIT PORTAL PIERS
100%
SPLIT PORTAL TIEBEAMS
100%
U GIRDER SPANS
64%
I GIRDER SPANS
12%
STEEL GIRDER SPANS
57%
HIGHLIGHTS:

  • 1st I-Girder of HSR Layout Station launched.
  • 1st U-Girder of HSR Layout Station launched.
  • 1st pier of Ibbaluru Station cast upto track level.
  • LG1 shifted from Kadubeesanahalli to HSR Flyover. Assembly ongoing.

DECEMBER

2024

ISSUES:

  • Permission pending from Traffic Department to start work on 1 pier at Silkboard. Staggered permission will be granted, so as to not affect traffic flow.
  • Slow Progress on common Portal Piers at Ibbaluru. Affected piers are ORP164, ORP165, ORP166, ORP167

Progress In The Month
U Girders Progress In Last 6 Months
STATIONS PROGRESS
Select Station:
DESCRIPTIONTOTALCOMPLETEDCOMPLETION
Piers GL To CCL
99
CCL Pier Cap
98
Pier CL To TL
96
PFL Pier Cap
94
PFL Arms
180
CCL Arms
1814
CCL RCC/I-Girders
480
PFL RCC/I-Girders
320
U Girders
160
Silkboard Station's Progress In 3D

USE MOUSE TO ZOOM, PAN, AND ROTATE THE MODEL. SCROLL TO ZOOM IN AND OUT. DRAG TO ROTATE. SHIFT+DRAG TO PAN. PINCH ZOOM ON MOBILE

NOTE ON STATION'S PROGRESS TABLE:
    • STATION'S PROGRESS BEING REPORTED CONSISTS ONLY OF MAIN GRID IN MEDIAN. OTHER THAN THIS, SECONDARY WING PIERS ON SERVICE ROAD MEDIAN, SECONDARY WING CAPS, GIRDERS, CONCOURSE SLAB, PLATFORM SLAB, SECONDARY WING SLAB, ENTRY/EXIT STRUCTURE COLUMNS, STAIRCASES, ROOMS, ROOF ETC WORKS ARE NOT BEING TRACKED AS THE SCOPE DATA IS NOT AVAILABLE AND ALSO DIFFICULT TO TRACK BY PUBLIC DUE TO VISIBILITY ISSUES.
  • SILKBOARD FLYOVER PROGRESS
    DESCRIPTIONRAMP DRAMP E
    TOTALCOMPLETEDTOTALCOMPLETED
    Piers
    393144
    Pier Caps
    331244
    Portal Beams
    30--
    I Girder Spans
    30643
    Steel Girder Spans
    50--
    Silkboard Flyover Map
    Flyover Map
    Girders Progress
    Girders Progress
    Gallery Image 1

    LG1 Shifted To HSR Flyover. Assembly Ongoing

    © Photo Copyright: Sunil
    Gallery Image 2

    Pier Caps Of Silkboard Flyover D Loop Being Launched Beside Silkboard Station

    © Photo Copyright: Sunil
    Gallery Image 3

    Viaduct Near Agara Flyover

    © Photo Copyright: Sunil
    Video Of Progress As Of Dec 8th 2024: By Sunil